AssetWise CONNECT Edition Help

The Contractor Initiated EWN Workflow

An early warning notification initiated by the Contractor (EWNC), indicates that the Contractor has notified the Project Manager of an early warning regarding a potential issue on the contract, that may have cost, time, and/or performance implications.

When risk actions are created and closed out, a Project Manager's Instruction (PMI) or Project Manager's Notification of Compensation Event (PMNCE) or a Contractor's Notification of Compensation Event (CNCE) may be initiated.

Communications, documents, files, and notes may also be associated with each EWNC.

Any AssetWise user who has the C_Commercial or PM_Commercial role is able to view this form.

The following diagram illustrates the workflow of tasks that are performed with a Contractor-initiated EWN:

AssetWise CONNECT Edition also prompts users to include various NEC3 contract clauses, at the appropriate times, ensuring compliance and accuracy.

To create a contractor initiated early warning notification, see To Create a Contractor EWN.

When the Initiate phase is completed, you can assign one or more actions to a group of users with a particular skillset, or to a specific user. For more information about assigning tasks, see Working with Tasks.